FAQ · Grid Infrastructure
How Does Data Center Grid Connection Work in Romania?
From ATR application to energisation — the complete process for large power consumers connecting to the Romanian transmission grid.
The Romanian Grid Connection Framework
Romania's high-voltage transmission grid is operated by Transelectrica SA. Large power consumers (≥1 MW) connect under ANRE Order 59/2013, which mandates the ATR (Aviz Tehnic de Racordare) technical approval process.
confirmed capacity
2 operational · 1 building
under ANRE 59/2013
Step-by-Step Process
- Connection Request — Developer submits application to Transelectrica with technical parameters (MW, voltage, load profile)
- ATR Study — Transelectrica models grid impact, defines connection point, required works (transformers, switchgear, protection systems)
- ATR Issuance — Technical approval issued with binding technical conditions
- Connection Agreement — Commercial contract specifying works, costs, and timeline
- Grid Works & Energisation — Developer funds agreed grid works; Transelectrica energises the connection
What 650 MVA Means at Resita
The Transelectrica substation adjacent to the Resita site operates at 400/220/110 kV with 650 MVA installed capacity. This means the physical infrastructure — transformers, protection systems, busbars — already exists and is operational. A data center developer applying for 50–200 MW consumer ATR at this node avoids the 2–4 year delay and €50–200M cost of building a new substation from scratch.
The ATR for this site was initiated in April 2026. The developer partner will receive the ATR results as part of the technical due diligence package.