FAQ · Regulatory
ATR Romania: Grid Connection Approval Process
The mandatory technical approval for connecting a data center to Romania's transmission grid — explained step by step.
What is ATR?
Aviz Tehnic de Racordare (ATR) is Romania's mandatory grid connection technical approval, governed by ANRE Order 59/2013. Without an ATR, no building permit for a grid-connected facility can be issued. The ATR defines:
- The maximum power allocation (MW) approved for the connection point
- The voltage level and connection topology
- Required grid works (new transformers, protection systems, cable/line construction)
- Cost estimate for grid works (borne by the consumer)
- Validity period (typically 24 months, extendable)
In Progress
April 2026
ATR initiated
at Resita site
at Resita site
6–12 mo
Typical study
duration
duration
ANRE 59/2013
Governing
regulation
regulation
ATR Process Steps
- Preliminary feasibility — Developer confirms site location and approximate MW requirement
- ATR Application — Submitted to Transelectrica (for ≥110 kV connections) with technical data sheet
- Transelectrica grid study — Load flow analysis, short-circuit study, stability assessment (6–12 months)
- ATR Document — Issued with binding technical conditions and works specification
- Connection Agreement — Commercial contract; developer funds the specified grid works
- Grid works construction — Developer or Transelectrica builds agreed infrastructure
- Energisation — Transelectrica connects and energises the point
Resita Site ATR Status
The ATR study for Resita Data was initiated in April 2026. The study covers a consumer connection at the adjacent 650 MVA Transelectrica substation (400/220/110 kV). The development partner will receive ATR results and associated cost estimates as part of the full technical due diligence package, covered by NDA.