FAQ · Regulatory

ATR Romania: Grid Connection Approval Process

The mandatory technical approval for connecting a data center to Romania's transmission grid — explained step by step.

What is ATR?

Aviz Tehnic de Racordare (ATR) is Romania's mandatory grid connection technical approval, governed by ANRE Order 59/2013. Without an ATR, no building permit for a grid-connected facility can be issued. The ATR defines:

  • The maximum power allocation (MW) approved for the connection point
  • The voltage level and connection topology
  • Required grid works (new transformers, protection systems, cable/line construction)
  • Cost estimate for grid works (borne by the consumer)
  • Validity period (typically 24 months, extendable)
In Progress
April 2026
ATR initiated
at Resita site
6–12 mo
Typical study
duration
ANRE 59/2013
Governing
regulation

ATR Process Steps

  1. Preliminary feasibility — Developer confirms site location and approximate MW requirement
  2. ATR Application — Submitted to Transelectrica (for ≥110 kV connections) with technical data sheet
  3. Transelectrica grid study — Load flow analysis, short-circuit study, stability assessment (6–12 months)
  4. ATR Document — Issued with binding technical conditions and works specification
  5. Connection Agreement — Commercial contract; developer funds the specified grid works
  6. Grid works construction — Developer or Transelectrica builds agreed infrastructure
  7. Energisation — Transelectrica connects and energises the point

Resita Site ATR Status

The ATR study for Resita Data was initiated in April 2026. The study covers a consumer connection at the adjacent 650 MVA Transelectrica substation (400/220/110 kV). The development partner will receive ATR results and associated cost estimates as part of the full technical due diligence package, covered by NDA.

Related: Grid connection overview · ATR glossary entry · Infrastructure page