Project Registry

Official document trail — verifiable, referenced, on file.

Every institutional engagement generates a document, and the index below covers the complete origination record for site RES1 — full copies are available in the data room under NDA.

ReferenceDocumentIssuing AuthorityDateStatus
AgreementStrategic partnership agreement with the MunicipalityMunicipiul ResitaMarch 2026Signed
Nr. 366*Mayor's Letter of Institutional Support (*registry number as referenced by the company; blank in the extracted copy on file)Primarul Municipiului Resita15.04.2026On file
DecreeDecree — Constitution of Technical Working GroupMunicipiul Resita30.04.2026Signed
Solicitare ATRRequest for connection information — Transelectrica (Nr. 42503)Resita Data Infrastructure SRL04.05.2026Replied
Nr. 23962Transelectrica Technical Response — grid technical info requestCNTEE Transelectrica SA25.05.2026On file
Nr. 29067Transelectrica reply to the company's request for connection options (request registered 29.05.2026)CNTEE Transelectrica SA18.06.2026Active · New
Solicitare E-DistRequest for connection information — E-Distributie BanatResita Data Infrastructure SRL04.05.2026Filed
CF Nr. 51122Land Registry Extract — Parcel RES1ANCPI / Cadastru RomaniaVerified 22.05.2026Verified
RES1 FactSheetInstitutional Fact Sheet — Site RES1Resita Data Infrastructure SRL2026On request
VerbalWater Supply Commitment — Barzava flow via municipal conduitMayor Ioan Popa, in personReported October 2026Verbal, written confirmation pending
WrittenFibre connection survey — route near Casa cu Tei, ~km 8Orange Business20.10.2026Survey starting; offer pending
Documents
Shared in stages under a mutual NDA
Company registration documents
Land registry extract
Grid correspondence with Transelectrica
Live Project Status

Development milestones — updated as they occur.

This section is updated in real time as official documents are received, agreements are signed, and key milestones are reached. All entries are date-stamped and document-referenced.

18.10.2024
Confidentiality Agreement signed — Marius Hudisteanu & Mayor Ioan Popa
The founding document of the project. Formal NDA signed between Marius Hudisteanu (as Romanian citizen and project initiator) and the Municipality of Resita, represented by Mayor Ioan Popa, with official municipal stamp and signature. Confirms Marius Hudisteanu's mandate as project initiator, coordinator and promoter. Remains in force.
03.2026
Strategic partnership agreement signed
Strategic partnership agreement signed and registered between Resita Data Infrastructure SRL and Primaria Municipiului Resita (Mayor Ioan Popa), establishing the institutional framework for Site RES1. The text is not published here; documents are shared under NDA.
07.04.2026
Resita Data Infrastructure SRL incorporated — CUI 54450187
Company registered at the Romanian Trade Registry. J-number J2026023286005. Marius Hudisteanu appointed Administrator and Legal Representative. The SRL becomes the legal vehicle for the 49-year concession and all regulatory rights.
15.04.2026
Mayor Letter of Support
Formal letter signed by Mayor Ioan Popa confirming municipal commitment to the data centre development and land allocation on the Calea Caransebesului industrial corridor. Referenced internally as Nr. 366; that registry number is blank in the extracted copy on file, so treat it as reported, not confirmed.
30.04.2026
Technical Working Group constituted — Mayoral Decree
Municipality of Resita formally constituted the Technical Working Group by Mayoral Decree (Mayor, Technical Director, Land & Patrimony Director, Investment Director) to coordinate the ATR process and concession framework.
25.05.2026
Transelectrica technical response — Nr. 23962
CNTEE Transelectrica SA replied to the company's request for technical information. Station-level capacity data are in official letter Nr. 29067/18.06.2026; Transelectrica inaugurated the substation on 26 May 2026.
04.05.2026
Grid connection information requests filed
Request for connection information submitted to Transelectrica (Nr. 42503); a parallel request was filed with E-Distributie Banat. Neither is an ATR application.
22.05.2026
Land registry extract verified — CF Nr. 51122
Official land registry extract confirmed. CF Nr. 51122, ~3 ha, Titular: Municipiul Resita. Encumbrances: NU SUNT (none). Unencumbered municipal public domain — concession eligible under Legea 50/1991.
29.05.2026
Connection request registered — Transelectrica reply Nr. 29067
Request for connection options registered with CNTEE Transelectrica SA on this date. Transelectrica replied on 18.06.2026 (Nr. 29067) with four connection alternatives, none selected. The grid solution study is not yet contracted; no ATR timeline is confirmed.
Approved by phone · no written resolution
Municipal Council concession vote — approved by phone
Concession award approved by Municipal Council (verified by phone with Oana Borza and Mayor Ioan Popa, 8 Oct 2026 — no written resolution/document on file yet); final signature by Resita Data Infrastructure SRL pending. Formal written resolution to follow in the data room once available.
2026–2027
ATR issuance — pending (partner-led)
Formal Aviz Tehnic de Racordare to be issued by Transelectrica following Studiu de Solutie review. No timeline confirmed. ATR process is partner-led.

Completed milestones: solid border. Pending milestones: dashed border. Page updated as events occur.

Management & Municipal Team

Technical Working Group — constituted by Mayoral Decree, 30 April 2026.

The data centre project is an initiative of the Municipality of Resita. The TWG is the formal operational body responsible for ATR coordination, the concession process, and institutional partner engagement, and all five members are named officials of the Municipality of Resita and Resita Data Infrastructure SRL (CUI 54450187), the legal vehicle. All TWG members are identified and reachable.

This team's expertise is in regulatory origination, municipal administrative process, and grid coordination — precisely the capabilities required to assemble this asset. Data centre engineering, CAPEX estimation, anchor tenant development, and construction management are the institutional partner's mandate. This is standard for origination-stage infrastructure assets: the originator delivers the regulatory and land framework; the operator delivers the technical and commercial build-out.

Administrator · Legal Representative · SRL

Marius Hudisteanu

Founder, Administrator, and Legal Representative of Resita Data Infrastructure SRL, managing administrative coordination between the municipality, regulatory bodies, and institutional counterparties, and overseeing documentation, the Virtual Data Room, and formal process compliance. Legal administrator of record (CUI 54450187).

Mayor · Municipality of Resita

Ioan Popa

Mayor of Resita, now serving a third consecutive mandate, and a civil engineer by training and profession. They initiated the confidentiality protocol (October 2024) that formally launched the data centre development process, and are co-signatory of the strategic partnership agreement (March 2026) and author of Mayor Letter of Support Nr. 366 (15.04.2026), as well as an active member of the Technical Working Group (Decree 30.04.2026). Under their administration, the Calea Caransebesului industrial corridor has been formally designated for large-scale infrastructure investment and listed in the national investor registry.

Investment Development · Municipality

Oana Borza

Director of Investment Development and Economic Strategy, Municipality of Resita, leading the institutional investor pipeline for the Calea Caransebesului industrial corridor. They are a signatory of key partnership documents between the municipality and Resita Data Infrastructure SRL, coordinate the municipal administrative interface with Transelectrica during the ATR grid connection process, and are a member of the Technical Working Group (Decree 30.04.2026).

Land & Patrimony Assessment

Gartoi Liviu

Municipal land and patrimony specialist, City of Resita, responsible for the official cadastral analysis and legal land documentation for parcel CF Nr. 51122 within the Calea Caransebesului industrial zone. They manage the patrimony and land register framework governing the 49-year administrative concession under Legea 50/1991, and are a member of the Technical Working Group constituted under Mayoral Decree (30.04.2026).

Technical Coordination

Lucian Barna

Technical Director, Municipality of Resita, coordinating the interdepartmental technical workflow between the municipal administration, Transelectrica, and E-Distributie Banat on behalf of the project. They are responsible for the technical feasibility assessment and administrative interface for the grid connection process, and are a member of the Technical Working Group constituted under Mayoral Decree (30.04.2026).

Direct Contact · Project Developer

For NDA requests, document access and institutional enquiries, write by email. One partner, direct process.

Press & Industry Recognition

Covered by the industry press. Listed on global data center registries.

Data Center Dynamics · Industry Press
"Plans announced for municipal data center in Resita, Romania"
DCD (Data Center Dynamics) — the world's leading data center industry publication — covered the Resita Data Infrastructure project, confirming the municipal partnership, the substation adjacency, and the active partner search process.
Read on Data Center Dynamics →