650 MVA installed (400/220/110 kV)ConfirmedEconomica.net ↗
Corridor 1 operational (117 km, Porțile de Fier → Reșița)ConfirmedThe Diplomat, Apr 2024 ↗
Corridor 2 operational, both circuits (131 km, Reșița → Pančevo)ConfirmedThe Diplomat, Jan 2025 ↗
4 EU PCI designations (ENTSO-E TYNDP P144)ConfirmedENTSO-E ↗
PPC Romania 100 MW adjacent acquisition (Dec 2025)ConfirmedProfit.ro ↗
Romania industrial electricity ~€0.14/kWh (EU avg ~€0.19)ConfirmedEurostat ↗
Corridor 3 under construction (Reșița → Timișoara)In progressElectromontaj SA · RON 309.5M
Transelectrica PDRET 2024–2033 — Reșița priority nodeIn progressEconomica.net ↗
50–200 MW consumer potential (preliminary only)PendingATR required · no commitment
Formal ATR grid studyPending6–12 months · ANRE 59/2013 · partner-led
~31 ha perimeter in municipal private domainConfirmedExtrase CF · DOMENIU PRIVAT · NU SUNT sarcini · under NDA
~3 ha project footprint identifiedConfirmedExact boundaries in municipal opportunity study
Industrial zoning — no rezoning requiredConfirmedReșița municipal industrial zone
No encumbrances on identified landConfirmedExtras CF section III · NU SUNT · under NDA
PUZ (Zonal Urban Plan)In progressUnder elaboration · Legea 350/2001 · subject to HCL approval
Municipal land allocation procedure initiatedIn progressHCL · ANEVAR valuation · public tender
Building Permit (AC)PendingPartner-led after PUZ + ATR · Legea 50/1991
EIA (Environmental Impact Assessment)PendingPre-screening: no apparent conflicts · full EIA by partner post-allocation
Resita Data Infrastructure SRL registeredConfirmedCUI 54450187 · J2026023286005 · 7 April 2026 · CAEN 7112
Strategic Partnership Agreement signed and registeredConfirmedSigned 27.03.2026 · City Hall Registry · full document under NDA
Institutional Support Letter Nr. 366/15.04.2026ConfirmedMayor Ioan Popa · official letterhead
LOI received from infrastructure fundIn progressActive discussions · documentation under NDA
Romania DC market 19.93% CAGR through 2031ConfirmedMordor Intelligence ↗
62% of investors favour opportunistic new developmentConfirmedCBRE Investor Survey 2025 ↗
EU DC vacancy forecast 6.5% by end 2026ConfirmedCBRE European Outlook 2026 ↗