400 kV grid · Reșița node

The infrastructure preceded the project.

The Transelectrica 400/220/110 kV node at Reșița was upgraded in 2024–2025. Three 400 kV corridors converge with four EU PCI designations. The project was located to be adjacent to this grid — not the other way round.

Every figure · public record/Installed ≠ available · ATR determines connectable MW
Illustrative · Not the Reșița facility
Illustrative · Not the Reșița facility

Substation schematic

What connects at Reșița 400.

650 MVA total: one 400/220 kV unit (400 MVA) and one 400/110 kV unit (250 MVA, upgraded 2024–2025).

RES · 400/220/110 kV · 650 MVA 400 kV BUSBAR Porțile de Fier117 km · 2024 ✓ Pančevo RS131 km · 2025 ✓ Timișoaraîn construcție 400/220 kV 400 MVA 400/110 kV 250 MVA 220 kV 110 kV ~3 ha site KM 7.5 · ATR PENDING PPC 100MW
Schematic · public recordRES · 2024–25 upgrade
Operational

Substation — 650 MVA installed

Economica.net, Nov 2024 ↗

Operational

Corridor 1 — Porțile de Fier → Reșița operational (117 km)

The Diplomat, Apr 2024 ↗

Operational

Corridor 2 — Reșița → Pančevo, both circuits operational (131 km)

The Diplomat, Jan 2025 ↗

Operational

4 EU PCI designations (ENTSO-E TYNDP P144)

ENTSO-E TYNDP P144 ↗

Operational

PPC Romania — 100 MW adjacent (Dec 2025)

Profit.ro ↗

Required · Pending

Corridor 3 — Reșița → Timișoara (under construction)

Electromontaj SA · RON 309.5M · expected 2027–2028

Required · Pending

Formal ATR grid study — Not yet initiated

6–12 months · ANRE Order 59/2013 · partner-led

Installed ≠ Available

What 650 MVA does and does not mean.

Confirmed

650 MVA installed

Transformer equipment physically installed, tested and energised. Transelectrica's investment — complete.

Pending

Available connectable MW

Depends on existing loads, N-1 contingency and new consumers. Only the formal ATR determines this figure.

Preliminary

50–200 MW indicative

Based on node scale and upgrade history. Informational only — binds nobody. ATR closes the gap.

Partner step

Partner commissions ATR

Development partner files with Transelectrica, supported by Institutional Support Letter. 6–12 months · ANRE 59/2013.

Request the full grid analysis and ATR timeline.