All figures from public records — Last updated March 2026

400 kV Power & Grid
at Reșița, Romania

The Reșița Data site in Banat Montan, Western Romania is adjacent to one of the most significant recent grid upgrades in the country: a newly upgraded 400/220/110 kV Transelectrica node at the convergence of three 400 kV corridors, with a cross-border interconnector to Serbia operational since January 2025.

Important: 650 MVA is the installed transformer capacity of the substation. It does not mean 650 MW are available to a data center. Actual connectable load for a large consumer requires a formal Transelectrica ATR grid study (6–12 months, ANRE Order 59/2013). No MW is confirmed or reserved without this study.
View Full Validation Ledger Request Technical Briefing
Operational — Public Records

Confirmed Grid Infrastructure

Pending — Partner Required

Milestones Requiring Action

  • Line 3: Reșița – Timișoara (400 kV, under construction) Third 400 kV corridor. Contract: RON 309.5M, Electromontaj SA (Transelectrica.ro). Completion estimated ~2027–2028. Will complete the three-corridor convergence at Reșița and further strengthen the grid position.
  • Transelectrica PDRET 2024–2033: Reșița Priority Node €1.9 billion grid development plan (Economica.net). Reșița designated as priority node on the Banat Axis in Transelectrica's 10-year plan. Signals continued investment in this node's strategic importance.
  • Formal ATR Grid Capacity Study (Application Required) This is the critical path item. Per ANRE Order 59/2013: large consumers (>50 MW) apply directly to Transelectrica for an ATR (Aviz Tehnic de Racordare — Technical Grid Connection Approval). Study duration: 6–12 months. This study determines actual connectable capacity, connection voltage level, technical requirements, and connection cost. No MW is confirmed or reserved without it. Initiating this study is the first action of the development partner.

Ready to Initiate the ATR Study?

The formal Transelectrica grid study is the first milestone. Reșița Data Infrastructure provides the site context, municipal access, and documentation. The developer leads the ATR application.

Request Technical Briefing View Validation Ledger